Maintaining Subcontract Information

SUBCONTRACT MANAGEMENT

1. MAINTAINING SUBCONTRACT INFORMATION

The purpose of the Subcontract module is to manage your subcontractor’s contracts, change orders and work performed. This information can be setup and managed from the Subcontract Cards.

From a job card, you can access the Subcontracts list for the specific job you are in.

For a complete list of your subcontract, you can search “Subcontracts” from the search Icon. Alternatively, if your role type is ProjectPro Manager, you can select the Subcontracts option from your role centre

Once selected, you will find a list of your subcontracts as we have shown below.

Select an existing subcontract to edit or create a new one.
A Subcontract Card is similar to a Job Card. Below we will detail each field and it’s use.

1.1 General Fast Tab:

FIELD COMMENTS:
No. Subcontract number – manual or automatic. To automatically assign the next available No. in your No. Series, tab off this field.
Description Enter Subcontract description.
Buy-From Vendor No. Enter vendor for the Subcontract
Buy-From Name Vendor name defaults from Vendor no. selected
Buy-From Address Vendor address defaults from Vendor no. selected
Buy-From Address 2 Vendor address defaults from Vendor no. selected
Buy-From City Vendor city defaults from Vendor no. selected
State Vendor State defaults from Vendor no. selected
Buy-from Zip Code Zip Code defaults from Vendor no. selected
Buy-from Contact Vendor contact defaults from Vendor no. selected
Sub-Level to Subcontract No. If this Subcontract is a subordinate to another Subcontract, then indicate what Subcontract
Search Description The Subcontract Description becomes the Search Description unless it is changed.
Person Responsible This field contains the code of the person responsible for the Subcontract. You can click the Assist Button in the field to see a list of resources.
Job No. The Job no for which this Subcontract is made
Last Date Modified This field shows when the job card was last modified.
When you change information on the Subcontract card, the program automatically updates the Last Date Modified field to show the current system date.

1.2 Subcontract Lines Fast Tab

You can assign Job Planning Lines to a subcontract by selecting “Get Job Budget Lines” from the ribbon. Your Job Planning Lines will be displayed on a new page for you to select from.

Choose the lines associated with this Subcontract and select “OK” to add them to the subcontract card.

You will notice the lines that were selected above are now available on the subcontract card in the “lines” section.

If you need to manually add a line to the subcontract card, you can do so from the “Lines” section.

Note: Manually added lines will affect only the subcontract card. These lines will not be updated on the Job Planning Lines and will not adjust the job budget.

Below we have detailed each column you will need to enter if you choose to enter a line manually. Note: depending on your personalized view, you may not see all of the fields below.

FIELD COMMENTS:
Job No. Select the Job No. the Subcontract is for
Job Task No. Select the Job Task No. associated with the Subcontract
Task Description Description related to the Job Task No.
Job Cost Category Select the subcontract Cost Category
Starting Date Enter the Subcontract starting date for the associated line.
Type This field contains the type of account to which the subcontract line relates.
The options are:
Blank, Item, G/L Account
No. This field contains the number of the account to which the Item Or G/L Account is posted, depending on the selection in the Type field.
You can see the numbers available by clicking the Assist Button in the field.
Description The application automatically displays the name of the item or G/L account to which this entry applies. You can change the description, a maximum of 50 characters, both numbers and letters, are allowed.
Quantity You can enter the number of units of the No., that is, the item or G/L account number, that should be specified on the line.
Direct Unit Cost Direct Unit Cost only shows if “Items” are being used.
Unit Cost This field contains the unit cost for the selected Type and No. on the line. Unit Cost is automatically retrieved of the selected Type and No. if the type is Item. If the type is G/L Account, unit cost is automatically retrieved if you have setup Unit Cost in the Job G/L account Prices window.
Total Cost This field is the calculated total of Quantity*Unit Cost
Work Units Optional – enter the Work Units being tracked
Work Unit of Measure Optional – enter the Unit of Measure for Work Units
Unit of Measure Code Unit of Measure for the Subcontract amount

1.3 Constants Fast Tab:

FIELD COMMENTS:
Vendor’s Job No Job no of the vendor if applicable
Creation Date Enter Subcontract creation date
Starting Date Enter Subcontract Start date
Ending Date Enter Subcontract End date
Completion Date When finished enter Subcontract Completion date
Retention Percent Enter Subcontract Retention Percentage
Status Select status of the Subcontract.
Options are: Planning, Quote, Order, Completed
Note: Your subcontract must have a status of “order” to post
Subcontract Class Specifies whether the subcontract card is a Master or a Change order

1.4 Manager Tab:

FIELD COMMENTS:
Reporting Status This status is like the Manager Job Status on our Job Card. This is for informational purposes only and can be adjusted as needed
Status Date This date will automatically update when the Reporting Status is changed
Estimated Start Date Estimated start date for this subcontract
Starting Date Starting date for this subcontract
Estimated Ending Date Estimated End date for this subcontract
Ending Date Estimated End date for this subcontract

1.4 Budget Fast Tab:

There were some changes in the Budget Tab on the Subcontract card and the changes are as follows:

If the “Actual Cost to Date” is Less than or equals to the “Total Budgeted Cost” then “Subcontract Variance” will not be calculated.

In the above pointer it is said that if the Actual Cost to Date is Less than or equals to the Total Budgeted Cost Then Subcontract Variance will not be calculated, as for the example in the below screenshot it is mentioned that the Actual Cost to Date is Equals to the Total Budgeted Cost then the Subcontract Variance is not Calculated.

If Actual Cost to Date is Greater than the Total Budget Cost then only the Subcontract Variance has been calculated.

But in the below case the Subcontract Variance has been calculated as the Actual Cost to Date is Greater than the Total Budget Cost, Subcontract Variance= (Actual Cost To date – Total budgeted Cost)

1.5 Costs Fast Tab:

1.6 Status Fast Tab: